Reference Class Forecasting for Hong Kong's Major Roadworks Projects
Abstract
Reference class forecasting is a method to remove optimism bias and strategic misrepresentation in infrastructure projects and programmes. In 2012 the Hong Kong government's Development Bureau commissioned a feasibility study on reference class forecasting in Hong Kong - a first for the Asia-Pacific region. This study involved 25 roadwork projects, for which forecast costs and durations were compared with actual outcomes. The analysis established and verified the statistical distribution of the forecast accuracy at various stages of project development, and benchmarked the projects against a sample of 863 similar projects. The study contributed to the understanding of how to improve forecasts by de-biasing early estimates, explicitly considering the risk appetite of decision makers, and safeguarding public funding allocation by balancing exceedance and under-use of project budgets.
Explore related subjects
Keep this discovery
Explore connections, maps & timelines
Bent Flyvbjerg, Chi-keung Hon, Wing Huen Fok. 2017-10-03. Reference Class Forecasting for Hong Kong's Major Roadworks Projects. https://doi.org/10.1680/jcien.15.00075
Cite the original work for its findings. Save a collection to share your selection of sources.