Why are Megaprojects, Including Nuclear Power Plants, Delivered Overbudget and Late? Reasons and Remedies

Abstract

In the first section, this report analyses Nuclear Power Plants (NPPs) in the context of megaprojects, explaining why they are often delivered over budget and late. In the second section, the report discusses how Small Modular Reactors (SMRs) might address these issues. Megaprojects are extremely risky and often implemented after a sub-optimal phase of project planning leading to underestimations of the costs and overestimation of short-term benefits. When considering adherence to schedule and budget, often megaprojects might be considered a failure, and optimism bias, strategic mis-rapresentation, complexity, poor planning, poor risk allocation, poor scope management are all reasons to explain their over budget and delay. For megaprojects, especially in the nuclear field, a key strategy to achieve good performances appears to be the standardization. This standardization needs to be twofold: (i) technical standardisation, i.e. the construction of very similar design over and over, and (ii) the project delivery chain standardisation, i.e. the same stakeholders involved in the delivery of a project that is replicable multiple times. Under this perspective, given their size and standardisation potential, SMRs, might be a suitable class of NPP for several countries. Yet, if the economy of scale is the only driver considered, SMRs are hardly competitive with large NPPs (or even with gas or coal power plants). However, a fleet of standard SMRs might balance the lack of economy of scale with the economy of multiples, and the delivery of several standardised SMR projects might be the key to achieve good project management performances in the nuclear sector. However, the deployment of SMRs faces a number of challenges from several perspectives, such as the licencing, supply chain and financing ones. These challenges might be enormous, but so are the potential rewards too.

Explore related subjects

Keep this discovery

BibTeXRIS

Giorgio Locatelli. 2018-02-16. Why are Megaprojects, Including Nuclear Power Plants, Delivered Overbudget and Late? Reasons and Remedies. https://arxiv.org/abs/1802.07312

Cite the original work for its findings. Save a collection to share your selection of sources.

KEEP EXPLORING

Related papers

Energy pathway variety and the progress of the energy transition in European countries

The integration of new energy forms into existing energy infrastructure has emerged as a critical challenge in the context of the pursuit of a sustainable energy transition. One of the main challenges is understanding how this integration takes place not only from the introduction, but also as energy follows existing paths or creates new ones through which it is transformed and used by different activities. Here we introduce techniques from network science to analyse this process for the case of 29 European countries between 1992 and 2021. We study how new energy forms increase or decrease the variety (heterogeneity) of paths through the system of each country by establishing new ones and replacing or phasing out existing ones. We find that the transition to systems based on renewable energy is characterised by an initial increase in the variety of paths while the heterogeneity of paths decreases at the end of the transition, when the proportion of non-renewables in the system tends to zero. We then demonstrate that greater heterogeneity (complexity) is associated with larger annual fluctuations in the proportion of non-renewable sources in the system, establishing a direct relationship between the progress of the transition and the complexity of the energy system in which it occurs. This contributes to the understanding of general properties of the dynamics of the energy transition and effects that accelerate or deter it.

physics.soc-ph

Fundamental limits to identifying node and tie memory in temporal networks: marginal artefacts and spreading dynamics

Temporal-network models attribute memory in contact data to either node self-excitation (branching ratio n_node) or tie reinforcement (kappa), carrying major consequences for epidemic spreading. We prove that when event initiators are observed, the two mechanisms are orthogonal: the Fisher information is block-diagonal and neither trades off against the other. In undirected proximity data, where initiators are unobserved, marginalising over them couples the mechanisms into a structural confound that survives posterior smoothing. On empirical proximity, messaging, and email records, however, a cruder failure dominates: fitted node memory is pinned to the inter-event marginal law and remains virtually invariant across latent label posterior samples (coefficient of variation below 1%). An inter-event-order shuffle test and burstiness-memory diagnostics reveal that exponential-Hawkes node memory is recovered from none, while tie reinforcement remains identifiable throughout. This near-unidentifiability is intrinsic, not an artefact of the exponential kernel: refitting flexible scale-free (sum-of-exponentials) kernels on synthetic power-law self-exciting processes fails to distinguish genuine node memory from memoryless renewal controls, with identical collapses recurring on algorithmic networks (edit bots, cloud microservices) and cortical spiking. Downstream epidemic consequences are quantitative: simulations fitted to empirical contact records under-predict outbreak sizes by up to a factor of 2.5 and shift the epidemic threshold. We conclude that observational temporal networks face a two-fold identifiability boundary: contact directionality is essential to decouple tie reinforcement, whereas heavy-tailed node self-excitation is intrinsically unidentifiable from contact timings alone.

physics.soc-ph

Assessing extreme flood impacts on urban rail transit: A passenger-oriented, resilience-informed framework

Urban rail transit systems (URTSs) are increasingly exposed to extreme floods following heavy precipitation, yet passenger travel impacts are often assessed through delay-based indicators that overlook infeasible journeys under large-scale disruptions. This study develops a passenger-oriented, resilience-informed framework for assessing flood impacts on URTS journeys from disruption onset to recovery completion. The framework presents a novel six-category classification of journey impacts, explicitly considering rerouting, alternative station use, and a delay threshold. It is demonstrated through hourly dynamic simulations of 15 London URTS lines under 30-year, 100-year, and 1,000-year flood risk scenarios. Results indicate that severe flood disruptions lead to substantial unsatisfied demand, driven primarily by unavailable routes rather than unacceptable delays. Compared with finer behaviour adjustments, rerouting dominates travel impacts. These findings highlight the significance of moving beyond delay-based assessment and provide valuable evidence on essential behavioural mechanisms for strategic-level stress testing intended to inform URTS flood resilience intervention planning.

physics.soc-ph