Experience with Long-pulse Operation of the PIP2IT Warm Front End
Abstract
The warm front end of the PIP2IT accelerator, assem-bled and commissioned at Fermilab, consists of a 15 mA DC, 30 keV H- ion source, a 2 m long Low Energy Beam Transport (LEBT) line, and a 2.1 MeV, 162.5 MHz CW RFQ, followed by a 10 m long Medium Energy Beam Transport (MEBT) line. A part of the commissioning efforts involves operation with the average beam power emulating the operation of the proposed PIP-II accelera-tor, which will have a duty factor of 1.1% or above. The maximum achieved power is 5 kW (2.1 MeV x 5 mA x 25 ms x 20 Hz). This paper describes the difficulties encoun-tered and some of the solutions that were implemented.
Explore related subjects
Keep this discovery
A. Shemyakin, J. -P. Carneiro, A. Chen, D. Frolov, B. Hanna, R. Neswold, L. Prost, G. Saewert, A. Saini, V. Scarpine, A. Warner, J. -Y. Wu, C. Richard. 2019-12-06. Experience with Long-pulse Operation of the PIP2IT Warm Front End. https://arxiv.org/abs/1912.03180
Cite the original work for its findings. Save a collection to share your selection of sources.