Tropical approximation to finish time of activity networks
Abstract
We breakdown complex projects into activities and their logical dependencies. We estimate the project finish time based on the activity durations and relations. However, adverse events trigger delay cascades shifting the finish time. Here I derive a tropical algebraic equation for the finish time of activity networks, encapsulating the principle of linear superposition of exogenous perturbations in the tropical sense. From the tropical algebraic equation I derive the finish time distribution with explicit reference to the distribution of exogenous delays and the network topology and geometry.
Explore related subjects
Keep this discovery
Alexei Vazquez. 2022-03-09. Tropical approximation to finish time of activity networks. https://doi.org/10.1103/physreve.106.l012301